Parklands Western Contract

Xyst was engaged by Greater Sydney Parklands (GSP) to prepare the Parklands West Landscape Maintenance Contract.

GSP required a procurement plan, tender documents and a performance based contract procured under a two-step EOI and RFT method, all to be completed within a short timeframe.

Xyst began the process by collating current asset data to form contract schedules and specifications, schedules of quantities and pricing estimates with the support of GSP. A procurement strategy was then formed and both contract and tender documentation was pieced together with GSP staff.

Xyst then assisted GSP as they accessed EOI and later RFT responses, a suitable contractor was then identified and negations were entered into by GSP.

Project Benefit

Xyst was engaged by Greater Sydney Parklands to procure a suitable contractor for its Western Parks.
Client organisation
Greater Sydney Parklands
Service Delivery
Maintenance contract procurement
Contract specifications
Levels of service setting